Slide#4 Costs
Costs:
- Modifications Computer Room
(480VAC, 3-Phase, 60amp): $4,598
- Network and Telephone connections: $11,691
- Summary: 8-Digital/1-Analog Phones and 40-10bT network lines
- 10-bT Break-down: move existing 25 from WPI, 10 SMVC, 1 new line.
- Digital Phone: $90/install, $30/month
- Analog Phone: $38/install, $37.75/month
- Network 10-bT: $100/install, $7.50/month
- CAVE Construction Costs: $40,000 (estimate high)
- CAVE Floor substructure: $40,000 (estimate high)
- Ceiling and floor project systems:
(future funding: $360,924)
- Floral Glass Panels:
(future funding: $12,200)
-
(Sub-Total future funding: $473,124)
- Moving costs: $2300
- Moving CAVE Computer: $400 (estimate 1/2-day)
- Installing transformer and electrical system: $500 (estimate 1-day)
- Projector platforms and mirror modifications: $400 (estimate)
- Moving existing furniture and CAVE system: $350 (estimate 3-days)
- Best programmable lock: $650
Total Cost: $58,589