Last Slide
Unresolved items:
- Electrical power modifications to CAVE computer room
ordered but not yet installed. (contact: Stephen Chapman)
- Furniture: ordered but not yet installed. (contact Rick Stocks)
- Communications ISR (Due May 15, 2000) ready to go:
Internet 10base-T, analog/digital telephones, and TV connections.
(contact: John Kelso ISR / Bill Blevins CNS)
- CAVE floor support structure design finished.
Installation completed no later than July 1, 2000. (contact Ron Kriz)
- Dynamic Test: Professor Tom Murray May 18, 2000.
Exact Move Date: July 17, 2000 (tenative) (contact Rick Stocks)
Classes begin Fall Semester in UVAG Lab: Monday August 21, 2000
- Scientific Visual Data Analysis: ESM4714 (Instructors: Kriz and Lockhart)
- Combined Research Curriculum Development: ESM5984 (Instructors: Batra, Kriz, Farkas)