ACITC UVAG 5-Year Operation Budget Request


Summary

Last Thursday, 10 April 1997, Len Peters, Vice Provost of Research & Dean of the Graduate School, Ken Reifsnider, Associate Director of Interdisciplinary Programs & Chairman of the CAVE Steering Committee and Ralph Byers, Director of Government Relations visited key Congressional contacts who indicated an opportunity for ACITC funding. Both John Fulton and Ken Reifsnider have requested a list from each of the ACITC authors in support of ACITC activities. After a personal discusion with Ken Reifsnider to get more of an idea about what such a list should include, I've simply added to the previous equipement list posted Jan 97 and posted a more itemized list that constitutes a 5-year operating budget for the UVAG below.

Note ,the previous Jan 97 equipment request was designed to establish a rough estimate of equipment that would be needed for the UVAG. The list posted below includes much more than just equipment and furniture. Please contact me at kriz@wave.esm.vt.edu if you want to comment, add or delete items from the list posted below. I know this list first appears to be an exercise in illusions of grandeur but it never hurts to ask.


ACITC UVAG 5-Year Operation Budget Request

  Item	 Quantity	Description				Cost Est., $ Apr 97

   1	     1	Onyx2 Infinite Reality, 12xR10000, 3GB memory,
		6-IR pipes, 12 RMs, 3 Racks (1999 CAVE upgrade 
		System) with 5 year warranty.			    $1,355,947.25

   2	    14	WT5-1P195MX14, Octane workstation, 20" CRT, 
		1xR10K, 4MB tex. RAM, 256MB RAM, 9GB disk,
		External CD-ROM, 5 year warranty		    $  617,321.50

   3	     1	R1-H6402-IR64-2, Onyx 2-IRs, 2xR10K, 20" CRT,
		9GB disk, 512MB RAM, 5 year warranty		
		System will be used for the I-Wall		    $  371,947.00

   4	     7	Electrohome Video Projects for I-Wall		    $  175,000.00

   5	    10	O2 workstation for offices,1xR10K, 17" CRT,
		64MB RAM, 4GB disk, 5 year warranty.		    $  174,276.50
						_________________________________
						SGI Hardware Total: $2,694,492.20

			      Non-SGI Workstations*

   6	     4	High-End Pentium Workstations for running Sense8
		and other visualization tools unique to NT systems  $  120,000.00

			SGI-Software for Lab and Offices

   7	    24	Varsity for worstations, $500/workstation	    $   12,000.00
   8	     1	Varsity for Onyx2, $1800/workstation		    $    1,800.00

		    Software (5-year site license maintenance)

   9	    50	AVS site licenses at $12.5K/yr			    $  175,000.00
  10	    14	PARADIGM: Vega site licenses at $3.5K/yr/seat	    $  245,000.00
  11	    14	Alias|Wavefront site licenses at $3K/yr/seat	    $  240,000.00
  12	    10	MSI site licenses at $5.5K/yr			    $   77,000.00
  13 unlimited	Sense8 site licenses at $12.55K/yr		    $   50,000.00
						  _______________________________
						  Software Total:   $  802,600.00
					 ________________________________________
					 Hardware/Software Total:   $3,617,092.20

				Personnel (5 years)

  14	    1	CAVE Programmer/Instructor, G16-1, $44K/yr	    $  220,000.00
  15	    1	CAVE system & Lab Mngr, G15-1, $40K/yr		    $  200,000.00
  16	    1	UVAG Coordinator, G10-1, $26K/yr		    $  130,000.00
  17	    2	Faculty release time AY & Summer, $112K/yr	    $  560,000.00
  18	    2	GRAs (including tuition), $48K/yr		    $  240,000.00
  19		Training, $5k/yr				    $   25,000.00
					_________________________________________
					Personnel & Training Total: $1,375,000.00

				Office Equipment & Expenses

  20	    3	Network Printers, $2K each			    $    6,000.00
  21	    1	Copy machine, (5 year maint), $35K		    $   35,000.00
  22	    1	FAX machine (5 year maint), $14K		    $   15,000.00
  23	    2	Personal Office computers + software		    $   11,000.00
  24	    2	Security systems				    $   12,000.00
  25	  26/4	10baseT / OC3 installation (5 years)		    $    5,190.00
  26		Office supplies, $3K/yr				    $   15,000.00
					_________________________________________
					Office equipment Total:	    $   99,190.00

				Furniture 2nd & 3rd Floor**

  27	    5	Office suite: desk, chairs, bookshelves, etc.	    $  150,000.00
  28	    1	Conference room: Table, 15 chairs, etc.		    $   16,000.00
  29	    14	Workstation tables with 28 chairs		    $   14,400.00
						_________________________________
						Furnitutre Total:   $  180,400.00

						_________________________________
						Total 5 Year Budget $5,271,682.20
___________________________________________________________
* This is a rough estimate on high end workstation that would run Sense8 software 
and other nonSGI CAVE compatible software.  A more accurate estimate will be 
given once someone at VT has configured such a system and can provide some 
quidance on what to buy.

** Estimated pices by telephone conversation. More accurate prices will be quoted 
here after we receive a quote from Harris Furniture.

Virginia Tech: http://www.sv.vt.edu/future/vt-cave/VT/UVAG_Oper_req.html
Revised April 13, 1997